October 14, 2026·5 min read

    PJM Capacity Prices for 2028/2029: What a $325/MW-Day Cap Means for Manufacturers

    By Kevin Topdjian

    PJM's capacity auction cleared at the cap again. For a manufacturer in PJM, the number that matters is your load in a handful of hours.

    On July 14, PJM's auction for the 2028/2029 delivery year cleared at $325 per MW-day, the FERC-approved cap, across the entire footprint. It procured 138,318 MW, which is 6,831 MW short of the reliability requirement, at a total cost of $16.4 billion. OPIS reports it is the third time the auction has cleared at the cap.

    PJM 2028/2029 capacity auction results at a glance

    • Clearing price: $325 per MW-day across the entire PJM footprint. That is the FERC-approved cap, and 2.5% below the prior auction's $333.44 cap.

    • Capacity procured: 138,318 MW, plus 10,864 MW from Fixed Resource Requirement regions, for 149,182 MW in total.

    • Shortfall: 6,831 MW below the reliability requirement.

    • Total value: $16.4 billion.

    • Without the price cap: PJM's own simulation shows the auction would have cleared at about $554.72 per MW-day, for close to $30 billion.

    • Delivery year: June 1, 2028 through May 31, 2029.

    • What's next: The price cap and floor also cover the 2029/2030 auction, which runs in December 2026.

    The cap is keeping prices flat for now, not low. If the cap is lifted after that auction, the uncapped number above shows which direction costs could move.

    What $325/MW-day means on a plant's meter

    $325 per MW-day times 365 days is $118,625 per MW-year. A facility carrying 2 MW of capacity obligation is looking at roughly $237,000 a year at the auction price. Your actual figure will differ with scaling factors, supplier margin and how your contract passes capacity through, but the order of magnitude is right.

    Your obligation is set by a few hours

    In PJM, the capacity obligation is driven by your load during a handful of the system's highest-demand summer hours, set from the prior summer. Most energy conversations focus on the energy price. Very few focus on those hours.

    What acting on it is worth

    Cut 10 percent of a 2 MW load during the peak hours and the obligation drops by 0.2 MW. At $118,625 per MW-year, that is about $23,700 a year, with no capital project required if the load can actually move: a chiller schedule, a compressor, a batch process, a charging window.

    The hard part is knowing which days are the peak days. You only know afterward, so the practical approach is forecasting the likely peak days and having a response plan ready for each one. Demand response was about 5 percent of the supply PJM procured in this auction, which tells you the market already values this flexibility. Most plants are simply not participating.

    This applies to PJM. Other regions price capacity and peak load through different mechanisms, so check your own market before copying the playbook.

    Sources: PJM: 2028/2029 capacity auction results (July 14, 2026) · PJM: 2028/2029 Base Residual Auction Report · OPIS: PJM's 2028/2029 auction clears at price cap for third time

    Related reading: Tariff clauses that change project ROI · FERC large-load rules and your rates